Delayed Task Summary

Delayed Task Summary

Introduction

The Delayed Tasks Summary report helps identify the tasks which have exceeded their Expected End Dates.


To view this report, you can go to: Home > Projects > Reports > Delayed Tasks Summary


The report is generated based on the Task Doctype.


Delayed Tasks Summary


Calculation of Delay 

Tasks have a date field called Completed On, which becomes visible when a Tasks status is changed to Completed.


Scenario 1

If a task is marked as Completed and the Completed On field is set, then the delay is calculated as the difference between the Completed On and the Expected End Date.


Delay = Completed On - Expected End Date


Scenario 2

If the Completed On field is not set, then the delay is calculated as the difference between the current date and the Expected End Date.


Delay = Current Date - Expected End Date


Chart

The chart shows the number of tasks that are On Track or Delayed based on the report generated after applying the filters.


Related Topics

  1. CRM Reports

  2. Job Card Summary

  3. Work Order Summary

  4. Work Order Consumed Materials

  5. Issued Items Against Work Order


    • Related Articles

    • Understanding Quality Inspection Summary Reports

      Overview This article gives you an overview of the Quality Inspection Summary Report. This report helps you monitor and analyze the quality of incoming, outgoing, and in-process items. 1. Accessing the Quality Inspection Summary Report To view the ...
    • iVendNext AI Copilot - Appendix

      Limits, defaults & glossary Default limits at a glance Setting Default Notes Requests per minute, per user 10 Configurable by administrator Requests per day, per user 200 Configurable by administrator Actions per question 15 Multi-step questions may ...
    • Integrating Quality Inspection with Inventory Management

      1. Overview Seamless integration between quality inspections and inventory management creates a closed-loop quality system that: ✔ Prevents defective stock from entering inventory ✔ Automates hold/release decisions based on QC results ✔ Maintains ...
    • BOM and Kits

      The Bill of Materials — The Design Document for Every Product In iVendNext Manufacturing, nothing gets made without a Bill of Materials. The BOM is the foundational document that defines exactly what goes into a finished good — every raw material, ...
    • Leveraging the Energy Point System for User Engagement

      Overview iVendNext’s Energy Point System uses gamification to boost engagement, reward contributions, and encourage friendly competition. Points earned for key actions help track performance and motivate teams. This article will walk you through ...